Windsor Gateway
Federal contribution
$130.9M
$130,944,635
Federal share47%
of $279.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 25, 2002
ApprovedMar 11, 2008
200320062009201220152018
Built
Approved 5.5 years after the announcement.
- Program
- Border Infrastructure Fund
- Ultimate recipient
- Province of Ontario
- Construction start
- Mar 11, 2008(actual)
- Construction end
- Mar 20, 2018(actual)
Against the original forecast
- Construction end22 months earlyforecast Jan 31, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13190 in the federal list. How to read these figures.