Onanole Sewer & Water System - Phase I
Federal contribution
$1.2M
$1,198,533
Federal share32%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 16, 2007
20082009201020112012
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Park
- Construction start
- Jan 1, 2009(actual)
- Construction end
- Feb 16, 2012(actual)
Against the original forecast
- Construction start23 months lateforecast Feb 1, 2007
- Construction end11 months lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13194 in the federal list. How to read these figures.