Alaska Highway Upgrade

Champagne Landing 10, Yukon

completeHighways and RoadsCSIF
Federal contribution
$15.0M
$15,000,000
Federal share50%

of $30.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 3, 2003
ApprovedMar 29, 2005
200420052006200720082009
Built

Approved 18 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Ultimate recipient
Government of Yukon
Construction start
Apr 1, 2004(actual)
Construction end
Oct 1, 2009(actual)

Against the original forecast

  • Construction end2.5 years earlyforecast Mar 31, 2012