Construction of a Community Centre

Apohaqui, New Brunswick

completeRecreationMRIF
Federal contribution
$109,136
Federal share33%

of $327.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2007
2008
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 6, 2007(actual)
Construction end
Jul 30, 2008(actual)

Against the original forecast

  • Construction end7 months lateforecast Dec 31, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13208 in the federal list. How to read these figures.