City of Summerside Wind Farm

Summerside, Prince Edward Island

completeGreen EnergyMRIF
Federal contribution
$1.9M
$1,904,231
Federal share33%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.1 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Summerside
Construction start
Feb 3, 2009(actual)
Construction end
Jan 24, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jan 16, 2009
  • Construction end8 weeks lateforecast Nov 30, 2009