New London Community Complex - Upgrading / Expansion

New London, Prince Edward Island

completeRecreationMRIF
Federal contribution
$85,618
Federal share33%

of $256.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Jan 31, 2006(actual)
Construction end
Oct 31, 2006(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 20, 2005
  • Construction end4 months lateforecast Jul 1, 2006

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13311 in the federal list. How to read these figures.