Thicket Portage Community Council - Water Treatment Plant
Federal contribution
$115,892
Federal share10%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 15, 2006
2007200920112013
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Thicket Portage
- Construction start
- Oct 1, 2012(actual)
- Construction end
- Mar 31, 2014(actual)
Against the original forecast
- Construction start5.6 years lateforecast Mar 1, 2007
- Construction end8 months lateforecast Jul 31, 2013
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13335 in the federal list. How to read these figures.