Rehabilitation of Pevensey Road Bridge
Federal contribution
$76,667
Federal share33%
of $230.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Armour
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Jun 13, 2007(actual)
Against the original forecast
- Construction start8 months lateforecast Aug 9, 2005
- Construction end2 months lateforecast Mar 31, 2007