Replacement of the Schuett Bridge
Federal contribution
$165,312
Federal share33%
of $495.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Woolwich
- Construction start
- Jul 1, 2006(actual)
- Construction end
- Jan 22, 2009(actual)
Against the original forecast
- Construction end13 months lateforecast Dec 31, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13505 in the federal list. How to read these figures.