Rehabilitation and Reconstruction of Three Arterial Roads and One Culvert
Federal contribution
$2.2M
$2,192,486
Federal share33%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
2007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Thunder Bay
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Jan 27, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 1, 2005
- Construction end4 months lateforecast Sep 30, 2009