Victoria Waste Water Sewer Treatment System
Victoria, Prince Edward Island
Federal contribution
$829,394
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Victoria
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Oct 31, 2008(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 20, 2005
- Construction end16 months lateforecast Jun 30, 2007