Reconstruction of Coldwater Road Corridor
Federal contribution
$703,873
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Orillia
- Construction start
- Apr 21, 2006(actual)
- Construction end
- Mar 9, 2009(actual)
Against the original forecast
- Construction end20 months lateforecast Jun 30, 2007
Also in Orillia
- Design and construct a new transit terminal$4.0M
- Construction of a Public Library and Market Square$1.9M
- Replace Conventional and Specialized Buses$1.8M
- Improvements to the Coldwater Water Distribution System$1.5M
- Upgrade the Wastewater Treatment Centre and Construct Tertiary Filter and Blower Buildings for Process Optimization, and Tertiary Treatment to meet Lake Simcoe Effluent phosphorus limits$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13809 in the federal list. How to read these figures.