Replacement of Cherry Avenue Bridge No. 11

Vineland, Ontario

completeHighways and RoadsMRIF
Federal contribution
$147,997
Federal share33%

of $444.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Lincoln
Construction start
May 1, 2006(actual)
Construction end
Aug 7, 2008(actual)

Against the original forecast

  • Construction end10 months lateforecast Oct 10, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13852 in the federal list. How to read these figures.