Greater Moncton Area Bypass

Dieppe, New Brunswick

completeHighways and RoadsCSIF
Federal contribution
$11.5M
$11,500,000
Federal share33%

of $34.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 19, 2004
ApprovedMay 18, 2006
20052006200720082009
Built

Approved 19 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Ultimate recipient
City of Moncton
Construction start
Nov 19, 2004(actual)
Construction end
Mar 31, 2009(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13880 in the federal list. How to read these figures.