Replacement of Roussin Road Bridge

Minnitaki, Ontario

completeHighways and RoadsMRIF
Federal contribution
$175,000
Federal share33%

of $525.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Machin
Construction start
May 15, 2006(actual)
Construction end
Feb 12, 2008(actual)

Against the original forecast

  • Construction end15 months lateforecast Oct 31, 2006

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13886 in the federal list. How to read these figures.