Replacement of Guelph Eramosa Bridges 13, 20 and 22
Federal contribution
$648,667
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
2007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Guelph/Eramosa
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Mar 29, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 1, 2005
- Construction end3 months lateforecast Dec 31, 2009
Also in Guelph/Eramosa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13922 in the federal list. How to read these figures.