Replacement of Guelph Eramosa Bridges 13, 20 and 22

Guelph/Eramosa, Ontario

completeHighways and RoadsMRIF
Federal contribution
$648,667
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
2007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Guelph/Eramosa
Construction start
Apr 20, 2006(actual)
Construction end
Mar 29, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 1, 2005
  • Construction end3 months lateforecast Dec 31, 2009

Also in Guelph/Eramosa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13922 in the federal list. How to read these figures.