Replacement of Culvert #086074
Federal contribution
$48,472
Federal share33%
of $145.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Perth
- Construction start
- Jun 14, 2006(actual)
- Construction end
- Feb 14, 2008(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 31, 2007
Also in Fullarton