Replacement of the Marlbank Culvert, Sherry's and Doran's Bridges
Federal contribution
$608,835
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Tweed
- Construction start
- May 8, 2006(actual)
- Construction end
- Jun 15, 2008(actual)
Against the original forecast
- Construction end8 months earlyforecast Feb 15, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13942 in the federal list. How to read these figures.