Replacement of the Marlbank Culvert, Sherry's and Doran's Bridges

Marlbank, Ontario

completeHighways and RoadsMRIF
Federal contribution
$608,835
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Tweed
Construction start
May 8, 2006(actual)
Construction end
Jun 15, 2008(actual)

Against the original forecast

  • Construction end8 months earlyforecast Feb 15, 2009