Upgrading of Bridges 1009, 1011 and 1013
Federal contribution
$347,390
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Tecumseh
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Mar 4, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2006
- Construction end20 months lateforecast Jun 30, 2007
Also in Tecumseh
- Town of Tecumseh Climate Change & Flooding Resiliency$10.7M
- Reconstruction of the Cedarwood Sanitary Pump Station to mitigate risk of basement flooding during storm events in Tecumseh, Ontario$3.6M
- Reconstruction and Expansion of Two Roads$3.3M
- Lesperance Road & Little River Boulevard Multi-Use Pathway$2.6M
- Construction of the Oldcastle Hamlet Wastewater Servicing System$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13943 in the federal list. How to read these figures.