Reconstruction of Simcoe County Priority Bridges
Federal contribution
$1.1M
$1,112,365
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Simcoe
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction end6 months lateforecast Sep 30, 2008