Implementation of Waste Management Strategy for Pelee Island Landfill

Pelee Island, Ontario

completeSolid Waste ManagementMRIF
Federal contribution
$410,131
Federal share45%

of $911.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008200920102011
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Pelee
Construction start
Apr 20, 2006(actual)
Construction end
Mar 10, 2011(actual)

Against the original forecast

  • Construction start9 months lateforecast Aug 1, 2005
  • Construction end3 weeks earlyforecast Mar 31, 2011