Replacement of Bridge 19

Mulmur, Ontario

completeHighways and RoadsMRIF
Federal contribution
$316,583
Federal share33%

of $949.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
2007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Mulmur
Construction start
May 1, 2006(actual)
Construction end
Feb 17, 2010(actual)

Against the original forecast

  • Construction start17 months lateforecast Dec 1, 2004
  • Construction end8 months earlyforecast Oct 31, 2010

Also in Mulmur