Rehabilitation of Jessop's Falls Bridge
Federal contribution
$666,667
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- United Counties of Prescott and Russell
- Construction start
- Sep 30, 2006(actual)
- Construction end
- Feb 19, 2009(actual)
Against the original forecast
- Construction end11 months lateforecast Mar 31, 2008
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13972 in the federal list. How to read these figures.