BST of 2Mile Community
Federal contribution
$138,978
Federal share33%
of $417.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2006
2007
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Liard First Nation
- Construction start
- May 23, 2007(actual)
- Construction end
- Jul 15, 2007(actual)
Against the original forecast
- Construction start12 months lateforecast May 15, 2006
- Construction end10 months lateforecast Aug 31, 2006