Torbay Bypass
Flatrock, Newfoundland and Labrador
Federal contribution
$5.0M
$5,000,000
Federal share50%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 22, 2007
ApprovedSep 5, 2008
200820092010201120122013
Built
Approved 16 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Province of Newfoundland and Labrador
- Construction start
- Jan 5, 2009(actual)
- Construction end
- Mar 26, 2013(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14211 in the federal list. How to read these figures.