Playground and Park Upgrade

Foxley River, Prince Edward Island

completeRecreationMRIF
Federal contribution
$6,620
Federal share32%

of $20.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 4, 2007(actual)
Construction end
Sep 28, 2007(actual)

Against the original forecast

  • Construction start10 months lateforecast Aug 15, 2006
  • Construction end10 months lateforecast Nov 30, 2006

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14225 in the federal list. How to read these figures.