Federal contribution
$1.4M
$1,357,453
Federal share41%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2007
2008200920102011
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 15, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2009
  • Construction end5 months lateforecast Oct 15, 2010