Water treatment plant
Federal contribution
$2.0M
$1,981,259
Federal share16%
of $12.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.3 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of La Tuque
- Construction start
- May 1, 2009(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction start18 months lateforecast Oct 31, 2007
- Construction end2.7 years lateforecast Apr 30, 2010
Also in La Tuque
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14304 in the federal list. How to read these figures.