Installation of wastewater collection network in the Village de East Farnham sector
Federal contribution
$893,776
Federal share31%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2006
200720082009201020112012
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of East Farnham
- Construction start
- Aug 21, 2007(actual)
- Construction end
- Dec 1, 2011(actual)
Against the original forecast
- Construction start20 months earlyforecast May 1, 2009
- Construction end8 months lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14311 in the federal list. How to read these figures.