Back to projects

Wastewater treatment

Sainte-Clotilde, Quebec

completeWastewaterMRIF
Federal contribution
$2.3M
$2,306,383
Federal share31%

of $7.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2006
20072008
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2007(actual)
Construction end
Mar 31, 2008(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14324 in the federal list. How to read these figures.