Wastewater treatment
Federal contribution
$2.3M
$2,306,383
Federal share31%
of $7.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2006
20072008
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Sainte-Clotilde-De-Châteauguay
- Construction start
- Apr 1, 2007(actual)
- Construction end
- Mar 31, 2008(actual)