Back to projects

Upgrade of municipal drinking water infrastructure

Chapais, Quebec

completeDrinking WaterMRIF
Federal contribution
$959,691
Federal share43%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 6, 2006
200720082009
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Chapais
Construction start
Feb 18, 2009(actual)
Construction end
Jun 15, 2009(actual)

Also in Chapais

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14370 in the federal list. How to read these figures.