Back to projects

Evaluation of the filtration plant and bringing it up to standards

Brownsburg-Chatham, Quebec

completeDrinking WaterMRIF
Federal contribution
$149,795
Federal share14%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 27, 2006
2007
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Brownsburg-Chatham
Construction start
Sep 15, 2006(actual)
Construction end
Apr 20, 2007(actual)

Also in Brownsburg-Chatham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14406 in the federal list. How to read these figures.