North Preston Water and Sewer
Federal contribution
$1.9M
$1,946,791
Federal share33%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2006
2007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Apr 19, 2010(actual)
Against the original forecast
- Construction end3 weeks lateforecast Mar 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14461 in the federal list. How to read these figures.