Drinking water treatment - Phase II
Federal contribution
$417,983
Federal share24%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 30, 2006
20072008200920102011
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Saint-Gervais
- Construction start
- Sep 26, 2006(actual)
- Construction end
- Sep 2, 2011(actual)
Against the original forecast
- Construction end3.7 years lateforecast Dec 31, 2007
Also in Saint-Gervais