South Queens Water Treatment Plant

Milton, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$2.3M
$2,250,000
Federal share33%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 9, 2006(actual)
Construction end
Oct 8, 2008(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 24, 2005
  • Construction end6 months earlyforecast Mar 31, 2009

Also in Milton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14544 in the federal list. How to read these figures.