Clark's Harbour Centre
Federal contribution
$142,731
Federal share23%
of $622.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2007
2008
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Clark's Harbour
- Construction start
- Jan 22, 2007(actual)
- Construction end
- Jan 16, 2008(actual)
Against the original forecast
- Construction start14 months lateforecast Nov 24, 2005
- Construction end14 months earlyforecast Mar 31, 2009
Also in Clark's Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14551 in the federal list. How to read these figures.