Villa Drive Sanitary Sewer
Federal contribution
$365,761
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2006
2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Sep 30, 2007(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 24, 2005
- Construction end6 months earlyforecast Mar 31, 2008
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14557 in the federal list. How to read these figures.