Crescent St . Water and Sewer, Sydney Mines
Federal contribution
$429,441
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Oct 15, 2009(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 24, 2005
- Construction end7 months lateforecast Mar 31, 2009
Also in Sydney Mines
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14559 in the federal list. How to read these figures.