Investment to bring up to standard Les Coteaux Water Filtration Plant
Federal contribution
$750,000
Federal share17%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 13, 2006
200720082009201020112012
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Les Coteaux
- Construction start
- Aug 22, 2006(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction start2.4 years earlyforecast Jan 1, 2009
Also in Les Coteaux
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14573 in the federal list. How to read these figures.