Construction of water filtration plant.
Federal contribution
$2.1M
$2,073,925
Federal share34%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 14, 2007
20072008
Built
Approved 14 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Fort-Coulonge
- Construction start
- Oct 1, 2007(actual)
- Construction end
- Aug 31, 2008(actual)