Construction of water filtration plant.

Fort-Coulonge, Quebec

completeDrinking WaterMRIF
Federal contribution
$2.1M
$2,073,925
Federal share34%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2007
20072008
Built

Approved 14 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Fort-Coulonge
Construction start
Oct 1, 2007(actual)
Construction end
Aug 31, 2008(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14574 in the federal list. How to read these figures.