Back to projects

Installing water and sewer systems

Saint-Joseph-de-Lepage, Quebec

completeDrinking WaterMRIF
Federal contribution
$549,677
Federal share28%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2008
200720082009201020112012
Built

Approved 20 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Sep 12, 2011(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 15, 2011