Kingsport Water System - Phase 1

Kingsport, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$545,346
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2007
2007200820092010
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 22, 2007(actual)
Construction end
Aug 18, 2010(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 24, 2005
  • Construction end5 months lateforecast Mar 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14649 in the federal list. How to read these figures.