Extending an interception main and building an aerated pond treatment plant (no. 2)

Lac-aux-Sables, Quebec

completeWastewaterMRIF
Federal contribution
$1.3M
$1,321,179
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2008
20092010201120122013
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 16, 2008(actual)
Construction end
Mar 31, 2013(actual)

Against the original forecast

  • Construction start2 years earlyforecast Jul 1, 2010
  • Construction end12 months lateforecast Mar 30, 2012

Also in Lac-aux-Sables

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14670 in the federal list. How to read these figures.