Orangedale Community Water Infrastructure
Federal contribution
$45,777
Federal share14%
of $321.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 10, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Orangedale Water Society
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Jan 20, 2009(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 24, 2005
- Construction end2 months earlyforecast Mar 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14676 in the federal list. How to read these figures.