Municipal Services Extension to Lively Subdivision

Halifax, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$1.4M
$1,439,300
Federal share24%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 8, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 28, 2006(actual)
Construction end
Feb 18, 2009(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 24, 2005
  • Construction end8 months lateforecast Jun 30, 2008

Also in Halifax