Municipal Services Extension to Lively Subdivision
Federal contribution
$1.4M
$1,439,300
Federal share24%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Feb 18, 2009(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 24, 2005
- Construction end8 months lateforecast Jun 30, 2008
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14677 in the federal list. How to read these figures.