Pier Road Sewer Upgrade - Phase 1
Federal contribution
$201,995
Federal share33%
of $606.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
2007200820092010
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Parrsboro
- Construction start
- Jan 22, 2007(actual)
- Construction end
- Mar 31, 2010(actual)
Against the original forecast
- Construction start14 months lateforecast Nov 24, 2005
- Construction end12 months lateforecast Mar 31, 2009