Vaudreuil Dorion drinking water supply, filtration plan expansion

Vaudreuil-Dorion, Quebec

completeDrinking WaterMRIF
Federal contribution
$375,000
Federal share15%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Vaudreuil-Dorion
Construction start
Nov 1, 2008(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start11 months earlyforecast Sep 21, 2009