Drinking water infrastructure

Piopolis, Quebec

completeDrinking WaterMRIF
Federal contribution
$1.1M
$1,089,210
Federal share35%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 8.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Piopolis
Construction start
Oct 1, 2009(actual)
Construction end
Oct 2, 2014(actual)

Against the original forecast

  • Construction start21 months lateforecast Jan 1, 2008
  • Construction end3.5 years lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14724 in the federal list. How to read these figures.