Drinking water infrastructure
Federal contribution
$1.1M
$1,089,210
Federal share35%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Piopolis
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Oct 2, 2014(actual)
Against the original forecast
- Construction start21 months lateforecast Jan 1, 2008
- Construction end3.5 years lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14724 in the federal list. How to read these figures.