Reservoir By-Pass
Hampden, Newfoundland and Labrador
Federal contribution
$37,062
Federal share33%
of $111.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2006
2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Hampden
- Construction start
- Dec 19, 2006(actual)
- Construction end
- Nov 30, 2007(actual)
Against the original forecast
- Construction start5 months earlyforecast Jun 1, 2007
- Construction end4 weeks lateforecast Nov 1, 2007
Also in Hampden
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14851 in the federal list. How to read these figures.