Reservoir By-Pass

Hampden, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$37,062
Federal share33%

of $111.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2006
2007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Hampden
Construction start
Dec 19, 2006(actual)
Construction end
Nov 30, 2007(actual)

Against the original forecast

  • Construction start5 months earlyforecast Jun 1, 2007
  • Construction end4 weeks lateforecast Nov 1, 2007

Also in Hampden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14851 in the federal list. How to read these figures.