Pumphouse Upgrade and Installation of Communal Drinking Water Dispensing Unit
Seldom-Little Seldom, Newfoundland and Labrador
Federal contribution
$158,625
Federal share32%
of $500.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2008
200820092010
Built
Approved 6 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Seldom-Little Seldom
- Construction start
- Sep 17, 2007(actual)
- Construction end
- Nov 30, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 1, 2007
- Construction end19 months lateforecast May 1, 2008
Also in Seldom-Little Seldom